1 |
Teesta Stage-II 330MW (Revised Capacity 150MW) |
Him Urja Infra Pvt. Ltd. |
01.03.2006 |
Project survey and Investigation not started due to opposition from Lachen Dzumsa. The project has now been revised and approved for implementation under Chungthang GP area only as Rangma HEP with capacity reduced to 150 MW. The Lol has been issued on 17.09.2012 |
2 |
Teesta Stage III 1200 MW |
Teesta Urja Ltd. |
18.07.2005 |
Project under construction and cumulative progress of the project till date is 89% |
3 |
Teesta Stage IV 520 MW |
NHPC Ltd. |
01.03.2006 |
Yet to start. No activities started at this site. |
4 |
Teesta Stage VI 500MW |
Lanco Energy Pvt. Ltd. |
07.12.2005 |
Most of the construction works stopped due to liquidity issues. Works in critical areas like HRT face 3A,3B ,4A and 4B have been resumed w.e.f 23/01/2014. Cumulative progress of the project till date is 46%. |
5 |
Pawan HEP 300MW |
Himagiri Hydro Energy Pvt. Ltd. |
05.12.2005 |
Only preliminary construction works started. National Wild Life Board clearance not obtained. 10kms of road upgradation and widening works of Sankalang-Bay-Sakyong road i/c construction of steel bridges under progress. Works undertaken by SPWD Roads and Bridges Deptt. GoS. |
6 |
Rongnichu HEP 96MW |
Madhya Bharat Power Corporation |
01.03.2006 |
Project under construction and progress till date is 23%. A PIL has been filed in the Hon'ble High Court of Sikkim for stay order to stop works at ADIT-II Face-5 in view of the day lighting which occurred there on 19/6/2013 |
7 |
Sada-Mangder HEP 71MW |
Gati Infrastructure Ltd. |
14.11.2003 |
Yet to start. No activities started at site. |
8 |
Bhasmey HEP 51MW |
Gati Infrastructure Ltd. |
14.11.2003 |
Project under construction and cumulative progress of the project till date is 28%. Progress of works at site is sluggish |
9 |
Rangit-II HEP 66MW |
Sikkim Hydro Ventures Ltd. |
08.12.2005 |
Construction works of project presently stopped due to liquidity issues. Actions to resume work immediately under active consideration. Cumulative progress of the project till date is about 8%. |
10 |
Rangit-IV HEP 120MW |
Jal Power Corporation Ltd. |
19.12.2005 |
Construction works of project presently stopped due to liquidity issues. Actions to resume work immediately under active consideration. Cumulative progress of the project till date is about 65% |
11 |
Dikchu HEP 96MW |
Sneha Kinitic Power Project Ltd. |
01.03.2006 |
Project under construction and cumulative progress of the project till date is 76% |
12 |
Jorethang Loop HEP 96MW |
DANS Energy Pvt. Ltd. |
05.12.2005 |
Project under construction and cumulative progress of the project till date is 88%. Process to start the dam and HRT is underway. |
13 |
Tashiding HEP 97MW |
Shiga Energy Pvt. Ltd. |
03.09.2008 |
Project under construction and cumulative progress of the project till date is 11%. PIL in Hon'ble High Court of Sikkim has directed MoEF, GoI to finalise the eco sensitive zone issue within 6 months i.e. by November 2014 |
14 |
Kalez Khola-I HEP 27.5MW |
Cosmic Infra Powergen Pvt. Ltd. |
22.03.2011 |
Preliminary survey and investigation works in progress. |
15 |
Kalez Khola-II HEP 54MW |
Pentacle Power Pvt. Ltd. |
25.04.2011 |
Preliminary survey and investigation works in progress. |
16 |
Rahi Khong HEP 25 MW |
Sikkim Engineering Pvt. Ltd. |
29.03.2012 |
Preliminary survey and investigation works in progress. |
17 |
Upper Rolep HEP 30 MW |
Cosmic Infra Powergen Pvt. Ltd. |
22.09.2012 |
Preliminary survey and investigation works in progress. |
18 |
Upper Rolep (Nathangchu) HEP 30MW |
Cosmic Infra Powergen Pvt. Ltd. |
22.09.2012 |
Preliminary survey and investigation works in progress. |
19 |
Rolep 36MW |
Velankani Renewable Energy Pvt. Ltd. |
Only LoI isued on 31/12/2010 |
Preliminary survey and investigation works in progress. |
20 |
Ralang 40MW |
Velankani Renewable Energy Pvt. Ltd. |
Only LoI issued 31/12/2010 |
Preliminary survey and investigation works in progress. |
21 |
Chakungchu 50MW |
Velankani Renewable Energy Pvt. Ltd. |
Only LoI issued 31/12/2010 |
Preliminary survey and investigation works in progress. |
22 |
Suntaleytar HEP 40MW |
Moser Baer Electric Power Ltd. |
Only LoI issued 23/02/2012 |
Preliminary survey and investigation works in progress. |
23 |
Rechu-Meyongchu HEP 26MW |
Planet Infra Projects Pvt. Ltd. |
Only LoI issued on Sept 2012 |
Preliminary survey and investigation works in progress. |
24 |
Rateychu-Bakchachu 40MW |
Samvijay Power & Allied Industried Ltd. |
Only LoI issued on 02.06.2012 |
Preliminary survey and investigation works in progress. |
25 |
Manul & Mangan 30MW |
HiGen Power Pvt. Ltd. |
Only LoI issued 22.09.2012 |
Preliminary survey and investigation works in progress. |
26 |
Rangit-III HEP 60MW |
NHPC Ltd. |
Project Commissioned |
|
27 |
Teesta-V HEP 510MW |
NHPC Ltd. |
Project Commissioned |
|
28 |
Chuzachen HEP 99MW |
Gati Infrastructure Ltd. |
14.11.2003 |
Project Completed and commissioned. COD declared as midnight of 17th June 2013. |